The New York State Department of Transportation (NYSDOT) is alerting motorists of upcoming road work on Route 13 in the village and town of Dryden, Tompkins County.

Beginning on Monday, June 30, NYSDOT crews will begin milling the pavement surface in both directions between the intersection of Springhouse Road and Route 366.  The milling work should take up to three days, regardless of the weather.  On Monday, July 7, crews plan to return to place a 1 inch layer of new asphalt on this nearly 4 mile section of road.  This work is weather-dependent and is expected to be completed by July 11.

Work will take place on weekdays between 8 a.m. and 6 p.m.  Traffic will be maintained on-site by flaggers during the milling and resurfacing phases.